Detail :: Data Jembatan
Jembatan Huai'an
Huai'an Bridge is a third ring road bridge across over the river in
Fuzhou. And it is also a landscape bridge in Fuzhou "West Gate". The
main bridge is a cable stayed bridge of steel-concrete combined girder
structure with dual-pylon and dual-cable plane. The main span length is
416m. The side span is made up of concrete beams with span layout of
112+416+112=640m. The bridge deck is 40m wide, two-way eight-lane, with
pavements at two sides. Superstructure of the main span is a structure
of flat steel box girder with total girder length of 396m, and girder
height of 3.5m in the center. Steel box girders with cross section of
three cells are connected by fully welding. Steel box girder for the
bridge is divided into 35 segments, among which there are two segments
of steel-concrete structure, two transit segments, 30-off standard
segments with length of 12.3m, and one connection segment in the mid
span. Total work amount of the whole bridge is 8040t.